Project Data :
Owner : PT. Menara Antam Sejahtera
Architect :
Site Area : m²
Building Area : 17.755 m²
Total Building :
Total Floor : 16 floor
Function Building :
Year : 2011
MEP System :
ACMV System : Central Air Cooled Chiller and Mechanical Ventilation System
Plumbing System :
- Clean Water,Waste Water, Ventilation and Rain Water. Etc
- Ground Water Tank (GWT) cap. 330 m3 (Source, PDAM and Deep Well)
- Top Reservoir cap. 40 m3
- STP cap. 130 m3/day, Aeration System
Fire Fighting System :
- Fire Hydrant, Sprinkler System and Fire Extinguisher
- Electric Hydrant Pump (EHP) 1.000 us gpm, head 150 m’
- Electrical Characteristic : 380 Volt, 3 Ph, 50 Hz.
- Lift / Elevator : 4 unit Passengers Lift, 1 unit service lift
Electrical System :
- Electrical Load : PLN 1.759 kVA (Source : PLN & Genset)
- Transformers Oil type : 1 x 1.600 kVA, 20 kV – 380 Volt
- Diesel Generator Set, 2 x 800 kVA Synchronized, Prime Power.
Lightning System : Non Conventional, Early Streamer Emission – Electrostatic type.
Telecommunication System : PABX-300 line outlets
Fire Alarm System : Semi Addressable System, 4 loops – 900 points
Sound System : Back Ground Music (BGM), Paging Speakers
Security System : CCTV System
Ancillary : Building Automation System (BAS)